Project
Schedule
Construction Facts:
Total Construction: 114,000 square feet
- New construction = 75,650 sq.
ft.
- Renovations = 38, 349 sq. ft.
- Construction and renovations to the existing East Building includes site development , site servicing and a new parking lot.
- Construction of the new building (North Wing) includes tie-ins to the existing building, new electrical room, Sterile Processing and distribution, Emergency Department, Medical Imaging (X-Ray) and Surgery.
Construction Tmeline:
- The Redevelopment project was awarded to Melloul-Blamey Construction on December 21, 2007
- The "Wall-Smashing" event signified construction start - January 10, 2008
- Construction of a new driveway will begin the week of Feb. 4th, 2008
- Hoarding of existing Cambria Street Visitors and Conestoga parking lots will begin as early as Feb. 19th, 2008. The Tower Crane will be onsite.
- The contractor bid on a 85-week schedule - Completion Summer of 2009.